RACI matrix: who does what on a project, with an example

Learn how to build a RACI matrix for a project: what Responsible, Accountable, Consulted and Informed mean, a worked example, and how it fits a Gantt chart.

6 min read

Most project confusion is not about dates. It is about people: who is doing this, who signs it off, who needed to be asked first, and who should have been told. A RACI matrix answers those four questions in one small table. This guide explains what a RACI matrix is, walks through an example for a real-sized project, and shows how to keep it in step with your Gantt chart so the two never tell different stories.

What a RACI matrix is

A RACI matrix is a grid. Tasks or deliverables go down the left side, people or roles go across the top, and each cell holds one letter that describes that person's part in that task.

  • R – Responsible. The person who does the work. There can be more than one, but fewer is better.
  • A – Accountable. The person who owns the outcome and approves it. There is exactly one per task.
  • C – Consulted. People whose input is needed before or during the work. This is a two-way conversation.
  • I – Informed. People who need to know about progress or the result. This is one-way: you tell them, they do not need to answer.

The point is not the letters themselves. The point is that writing them down forces decisions you would otherwise discover in the middle of the project, usually when something is late.

When a RACI matrix is worth the effort

A RACI matrix earns its place when:

  • More than three or four people touch the project.
  • Someone outside the team, such as a client, a legal reviewer or another department, has to approve things.
  • Handoffs between people are where delays usually happen.
  • You have already had a "I thought you were doing that" moment.

For a two-person side project it is overkill. A single owner name on each task is enough, which is what our guide on how to assign tasks to team members covers.

A RACI matrix example

Imagine a small team building a customer onboarding portal for a client. Five people are involved:

  • Ana, project lead on the agency side
  • Ben, developer
  • Chloe, designer
  • Dev, marketing manager at the client
  • Eva, the client's legal reviewer

The plan has about a dozen tasks across three phases. Here is the RACI matrix for the main deliverables:

Task Ana Ben Chloe Dev Eva
Gather requirements A C C R I
Design screens A C R C I
Write welcome copy C I C A/R C
Build portal A R C I I
Privacy and terms review I C I A R
User testing A R R C I
Launch R R I A I

A few things are worth noticing.

Every row has exactly one A. The launch, for example, is Dev's call because it is the client's portal, even though Ana and Ben do the actual work. If a row has two A's, nobody really owns it. If it has none, the task will drift.

A and R can be the same person. Dev both writes and approves the welcome copy. That is fine for small tasks. It just means nobody else signs it off, so make sure that is intended.

The client appears as R and A, not only as I. Clients are often treated as people to keep informed, when in fact they own several approvals. Writing that down early prevents the classic delay where the build is finished and nobody on the client side knew they had to sign it off.

Eva is mostly I. She only needs to act on one task. Listing her as Informed elsewhere means she gets the updates she needs without being pulled into every meeting.

How to build a RACI matrix in five steps

1. List the deliverables, not every task

Use the phases or the larger tasks from your plan, not the 40 smallest steps. Five to fifteen rows is a good size. If you already have a work breakdown structure, its second level is usually the right detail.

2. List roles or names

Use real names when the team is small and stable. Use roles ("client approver", "backend developer") when people change or when the matrix is a template you will reuse.

3. Fill in the A column first

For each row, ask: who will be blamed, or thanked, for this result? That person is A. Doing this first exposes the hardest conversations early, because the A is where most disagreements live.

4. Add R, then C and I

Next, mark who does the work. Then mark who must be asked, and who must be told. Be strict with C. Every C is a conversation, and a row with five C's will be slow.

5. Review it with everyone in it

Send the matrix to every person listed and ask them to check their own column. Someone will say "I can't approve that, my manager does", and that is exactly what you want to find out now rather than the week before launch.

Common RACI mistakes

  • Too many R's. If four people are Responsible, nobody is. Split the task into smaller pieces with one main R each.
  • Too many C's. Consulting everyone feels inclusive but adds days to every decision. Move people to I when they only need to know.
  • Columns full of letters. If one person has an R or A on nearly every row, they are the bottleneck. Look at their workload before the project starts.
  • A matrix nobody looks at again. A RACI built in the kickoff and then forgotten is just paperwork. Keep it short so it stays useful.

How a RACI matrix fits with a Gantt chart

A RACI matrix and a Gantt chart answer different questions. The RACI says who plays which part. The Gantt chart says what happens when and in what order. They work best side by side, as long as they do not contradict each other.

In ProGantt Flow you can carry the most important parts of the RACI into the plan itself:

  • Responsible on the task. Add each person as a resource and assign them to the tasks where they are R. The chart then shows who is doing what, and you can spot overlapping bars for the same person.
  • Accountable and Consulted in notes or tags. Task notes are a good place for "Approved by Dev" or "Check with Eva before starting". If an approval step really takes time, make it its own task, such as "Client sign-off on designs", so it shows on the timeline.
  • Informed through sharing. People who only need to follow progress can be invited as viewers. They see the same live schedule as the team without being able to change it. Our guide to editor vs viewer access explains how to choose roles.
  • Approvals as milestones. Big sign-offs, such as "Legal approval" or "Go-live decision", work well as milestones, so everyone sees the date by which the Accountable person has to decide.

The matrix itself can stay in a short document or a table at the top of your project notes. What matters is that the names on the Gantt chart match the R's in the matrix.

Checking the matrix against the plan with an AI agent

If you manage the plan through an AI assistant connected over MCP, you can ask it to cross-check the two. For example: "In my Onboarding portal project, list each person's tasks and person-days for the next three weeks" or "Which tasks have no one assigned?" The assistant can read assignments and per-person load from the plan, and you compare the result with your RACI. The connector docs list what the assistant can read and change.

A quick RACI template

Copy this and replace the rows and names:

Deliverable Project lead Doer Reviewer Client Other stakeholders
Requirements A C C R I
Design A C R C I
Build A R C I I
Review and approval C I R A I
Launch R R I A I

Then check three rules before you share it: one A per row, at least one R per row, and no person carrying an R or A on almost every row.

Summary

A RACI matrix is a simple table that makes roles explicit: who does the work, who owns the result, who is asked and who is told. Build it from your main deliverables, fill in the Accountable column first, keep Consulted lists short, and review it with everyone it names. Then put the Responsible names on the tasks in your Gantt chart, so the schedule and the roles always agree.